Orezone Gold Reports Third Quarter 2026 Results

Selasa, 17 November 2026 | 20:55:24 WIB
Orezone Gold Corporation

All dollar amounts are in USD unless otherwise indicated

VANCOUVER, British Columbia, Nov. 16, 2026 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to report its operational and financial results for the third quarter of 2026.  The Company will host a conference call and webcast today at 3:00pm PT / 5:00pm ET to discuss the results.  Details to join the conference call and webcast are provided at the end of this release.  In this release, abbreviations “M” means millions, “K” means thousands, and “9M” means first nine months.

Third Quarter 2026 Highlights:

  • Reported record quarterly gold production of 59,674 oz.  Gold sales totaled 56,461 oz at an average realized gold price1 of $4,174 per oz.

     
  • Reported All-In Sustaining Costs1 (“AISC”) of $2,475 per gold oz sold.

     
  • Generated revenue of $238.5M and Adjusted EBITDA1 of $111.8M.

     
  • Delivered net earnings of $28.0M and basic earnings per share of $0.04 attributable to Orezone shareholders.  Net earnings in the current quarter were negatively impacted by a deferred tax expense of $15.8M mainly as a result of an updated assessment of the recoverability of the income taxes on Casa Berardi’s environmental rehabilitation provision at the end of mine life, based on the updated life-of-mine (“LOM”).

     
  • Generated operating cash flow of $71.1M, ending the quarter with a combined cash and bullion position of $147.2M, compromising $116.2M in cash and 7,433 oz of bullion with a market value of $31.0M.

     
  • Announced the results of an updated LOM plan and preliminary economic assessment (“PEA”) for Casa Berardi, highlighting a 14-year mine life with 116,000 oz of average annual gold production, 1,630,000 oz of total production, and an after-tax NPV5% of $1.05 billion using base case consensus gold prices.

     
  • Continued to advance work on a PEA of the Heva-Hosco development project, located along the Cadillac-Larder Lake Break, with release of study results expected by the end of 2026.

     
  • Released additional drill results across multiple zones for Bomboré, demonstrating the growth potential of the deposit and continuity of gold mineralization beyond current mineral resources and reserves (refer to the Company’s news release on August 11, 2026 for further details).

     
  • Reached substantial completion of Bomboré Stage 2A hard rock expansion with the commissioning of the rock breaker in July, followed by the post quarter-end commissioning of the oxygen plant in October and the thickener in November.

     
  • Appointment of Sophie Bertrand as Vice President, Sustainability, and Christian Bruneau as Vice President, General Manager of Orezone Quebec, adding to the Company’s experienced leadership team and operational capabilities in support of the Company’s future growth plans and current operations.

     
  • Conversion of all outstanding convertible notes by the note holders, with an aggregate principal of $35M, into 50 million common shares of the Company on September 16, 2026. 

     
  • Repaid the Phase I senior secured term loan owing to Coris Bank by making the final monthly loan payment at quarter-end, thereby extinguishing all remaining project debt used to construct the Phase I oxide operations at Bomboré.

________________________________
1 Non-IFRS measure.  See “Non-IFRS Measures” section below for additional information.
 


Patrick Downey, President and CEO, commented, “Orezone delivered record gold production in the third quarter, generating strong operating cash flow and increasing our cash balance. With higher-grades now being mined at both Bomboré and Casa Berardi, mill feed grades are expected to improve in support of another record quarter of gold production in Q4. We remain on target to achieve our 2026 production guidance.

At Bomboré, the Stage 2A hard rock expansion was completed under budget with the rock breaker and oxygen plant now fully operational and the thickener in early service. At Casa Berardi, the recently announced life-of-mine plan outlined a 14-year production profile, and we continue to advance underground development and exploration to rebuild the high-grade stope inventory. Looking ahead, we expect to release further exploration results from both Bomboré and Casa Berardi, along with the Heva-Hosco PEA, by year-end.”

Highlights for the Quarter Ended September 30, 2026

(All mine site figures on a 100% basis) Q3-2026Q3-20259M-20269M-2025
Operating Performance     
Gold productionoz59,67423,371 157,02979,607 
Gold salesoz56,46120,350 155,07777,558 
Average realized gold price1,3$/oz4,1743,375 4,4373,166 
Cash costs per gold ounce sold1$/oz2,0981,737 2,1081,500 
All-in sustaining costs1 per gold ounce sold$/oz2,4751,958 2,4091,709 
Financial Performance     
Revenue$000’s238,52368,947 696,094246,174 
Earnings from mine operations$000’s91,60526,450 295,909104,964 
Net earnings attributable to shareholders of Orezone$000’s28,0385,432 112,81437,317 
Net earnings per common share attributable to Orezone shareholders       
Basic$0.04
 
0.01 0.17
 
0.07 
Diluted$0.04
 
0.01 0.17
 
0.06 
EBITDA1$000’s113,58528,871 324,169110,323 
Adjusted EBITDA1$000’s111,84428,403 340,550118,090 
Adjusted earnings attributable to shareholders of Orezone1$000’s26,4945,022 124,55044,339 
Adjusted earnings per share attributable to shareholders of Orezone1$0.040.01 0.190.08 
Cash and Cash Flow Data     
Operating cash flow before changes in working capital2$000’s95,06021,602 375,77888,611 
Operating cash flow2$000’s71,0692,819 355,98946,880 
Free cash flow1$000’s49,231(31,914)155,116(55,386)
Cash, end of period$000’s116,24585,335 116,24585,335 

1 Average realized gold price, Cash costs, AISC, EBITDA, Adjusted EBITDA, Adjusted earnings, Adjusted earnings per share, and Free cash flow are non-IFRS measures.  See “Non-IFRS Measures” section below for additional information.
2 Cash flow from operating activities includes the $100M upfront deposit received in March 2026 on the gold stream from a subsidiary of Franco-Nevada Corporation (“Franco-Nevada”) as part of the financing for the Casa Berardi acquisition.
3 Average realized gold price shown includes the impact of the Casa Berardi gold stream with Franco-Nevada. 

9M-2026 RESULTS COMPARED TO 2026 GUIDANCE

Consolidated guidance shown in the table below is made on a 100% basis for the Company’s two operating mines.  The guidance reflects a full year of operations for the Bomboré Mine and the post-acquisition period of March 25 to December 31, 2026 for the Casa Berardi mine.

Mines on a 100% BasisUnit2026 Guidance9M-2026 Actuals
Gold productionAu oz222,000 – 247,000157,029
All-In Sustaining Costs1,2$/oz Au sold$2,200 - $2,400$2,409
Sustaining capital$M$58 - $62$36.5
Growth capital$M$49 - $58$38.0

1.   Non-IFRS measure.  See “Non-IFRS Measures” section below for additional information.
2.   AISC per gold oz sold excludes Purchase Price Allocation (“PPA”) adjustments on the Casa Berardi acquisition for stockpile processed and gold inventory sold.

BOMBORE GROWTH CAPITAL

No.Growth Capital DescriptionUnit2026 Original
Guidance
2026 Revised
Guidance
9M-2026
Actuals
IHard Rock Expansion – Stage 2A$M$15 - $18$14 - $16$10.4
IITSF Footprint Expansion – Cell 2$M$9 - $11$9 - $11$10.8
IIIResettlement Action Plan (“RAP”)$M$20 - $23$16 - $19$11.8
IVTSF Future Lifts (see below)$M$nil$5 - $6$2.6
 Total1$M$44 - $52$44 - $52$35.6

1.   The 2026 guided range for total growth capital has not changed as the forecasted cost underruns for the Stage 2A expansion and RAP are expected to offset the additional capital for the TSF future lifts.
 

  1. Hard Rock Expansion – Stage 2A (9M-2026 actuals: $10.4M)

    Stage 1 of the hard rock expansion saw the construction of a 2.5 Mtpa hard rock process plant in Q4-2025.  For 2026, the Company has allocated capital toward the installation of several components (“Stage 2A”) that will optimize the Stage 1 hard rock mill recovery and reliability, consisting of a rock breaker, thickener, and oxygen plant. 

    The rock breaker was commissioned in July while the oxygen plant was placed into service in early October.   Construction of the thickener followed by tie-in to the main hard rock plant was completed in late October.  The thickener is now operational after its commissioning in November.

    The Company is following a measured capital investment strategy for the balance of the Stage 2 construction (“Stage 2B”), the timing of which remains under review.  Stage 2B is designed to increase the plant nameplate from 2.5 Mtpa to 5.5 Mtpa.

     
  2. Tailings Storage Facility (“TSF”) Footprint Expansion – Cell 2 (9M-2026 actuals: $10.8M)

    Expansion of the TSF footprint southwards into Cell 2 commenced in 2025.  Cell 2 was HDPE lined and designed with an underdrainage network to improve water recovery and storage capacity.  Tailings deposition into Cell 2 began in June 2026.

     
  3. Resettlement Action Plan (9M-2026 actuals: $11.8M)

    RAP Phase IV is included in the Environmental and Social Impact Assessment (“ESIA”) submitted by the Company in 2024 to expand the current mining permit by an additional 7.65 km2. 

    Construction works scheduled in 2026 include private and public structures for household relocations to the BV2 and MV2 resettlement site extensions by October, and the start of the MV3 resettlement site extension in Q4-2026.  A diversion channel, community reservoir, and permanent haul bridge over the Bomboré river are also being constructed to provide year-round mining access to the P17 pit.

    Construction of the BV2 extension and the MV2 extension were completed in March and October, respectively, with local RAP contractors now mobilizing to the MV3 extension in November.  Main civil infrastructure consisting of the Bomboré bridge, P17 diversion channel, and community reservoir were completed in June.

     
  4. TSF Future Lifts (9M-2026 actuals: $2.6M)

    Annual lifts of the tailings embankments are required each year to create additional storage capacity for continuous tailings deposition over the life-of-mine.  Stage 6, being the second lift of Cell 2, commenced construction in Q2-2026 with costs reported under sustaining capital.  Due to the availability of additional nearby waste from mining for construction, the Company has accelerated works on the foundation and embankments of future lifts.  This acceleration of works will increase growth capital spending for tailings in the current year but will save on life-of-mine tailings construction costs by reducing rehandling of fill material.

     

CASA BERARDI MINE, CANADA

The 2026 guidance for Casa Berardi covers the post-acquisition period of March 25 to December 31, 2026.

Casa Berardi MineUnit2026 Guidance2,39M-2026 Actuals
Gold productionAu oz62,000 – 67,00040,841
All-In Sustaining Costs1,2,3$/oz Au sold$2,600 - $2,800$2,662
Sustaining capital1,2$M$37 - $39$19.7
Growth capital1,2$M$5 - $6$2.4

1.   Non-IFRS measure.  See “Non-IFRS Measures” section below for additional information.
2.    CAD/USD foreign exchange rate of 1.35 used to forecast cost metrics.
3.    AISC per gold oz sold excludes PPA adjustments for stockpile processed and gold inventory sold

Gold production incorporates both underground and open pit operations with quarterly gold production scheduled to be lowest in Q3-2026 from lower planned head grades caused by mine sequencing in the open pit and the drawdown of stockpiles. Production is expected to increase in the fourth quarter from better feed grades attributable to the mining of higher-grade open pit ore, and increased underground ore as underground development, labour, and equipment continue to ramp-up. Acceleration of underground lateral development is now being realized with development metres averaging over 15 metres per day in October from an average of 11 metres per day in the prior two quarters.

AISC in 2026 reflects lower underground feed grades and tonnes as the Company advances development in order to re-establish an inventory of higher-grade stopes for mining in future years. In addition, the IFRS Accounting Standards followed by the Company for the Casa Berardi acquisition require that gold inventories and ore stockpiles be increased to their estimated closing date fair values (“PPA adjustments”). The sale of the gold inventory and the processing of ore stockpiles in 2026 will impact cost of sales and, therefore, AISC otherwise reported.  These non-recurring, non-cash accounting adjustments have been excluded from AISC as they are not representative of the operating performance of the mine.

Sustaining capital will be focussed towards accelerated underground development, purchase of new underground mining equipment, tailings lifts, and process plant improvements.  Growth capital is primarily for engineering, technical studies, and permitting in support of future mine development.

OPERATING HIGHLIGHTS – BOMBORE MINE

Bomboré Mine, Burkina Faso (100% basis) Q3-2026 Q3-2025 9M-2026 9M-2025 
Safety     
Lost-time injuries frequency rateper 1M hours0.00 0.00 0.15 0.20 
Personnel-hours worked000’s hours2,338 1,921 6,551 5,102 
Mining Physicals     
Ore tonnes minedtonnes2,126,096 2,028,840 6,963,067 6,202,519 
Waste tonnes minedtonnes4,765,866 2,444,868 16,352,470 10,411,952 
Total tonnes minedtonnes6,891,962 4,473,708 23,315,537 16,614,471 
Strip ratiowaste:ore2.24 1.21 2.35 1.68 
Processing Physicals     
Ore tonnes milledtonnes2,542,463 1,523,697 7,399,104 4,600,023 
Head grade milledAu g/t0.57 0.55 0.56 0.62 
Recovery rate%86.6 87.0 86.6 87.6 
Gold producedAu oz40,562 23,371 116,188 79,607 
Unit Cash Cost     
Mining cost per tonne$/tonne5.16 4.45 3.94 3.42 
Mining cost per ore tonne processed$/tonne12.41 9.32 11.12 8.96 
Processing cost$/tonne9.85 8.94 10.00 8.81 
Site general and admin (“G&A”) cost$/tonne3.26 4.06 3.20 4.07 
Cash cost per ore tonne processed$/tonne25.52 22.32 24.32 21.84 
Cash Costs and AISC     
Mining cost (net of stockpile movements)$000’s31,560 14,194 82,314 41,239 
Processing cost$000’s25,041 13,627 74,013 40,509 
Site G&A cost$000’s8,287 6,187 23,646 18,735 
Refining and transport cost$000’s133 111 582 390 
Government royalty cost$000’s18,916 6,367 62,149 21,335 
Gold inventory movements$000’s(1,435)(5,142)(1,062)(5,887)
Site cash costs1 on a sales basis$000’s82,502 35,344 241,642 116,321 
Sustaining capital$000’s5,517 2,532 16,842 10,015 
Sustaining leases$000’s44 46 136 137 
Site AISC1 on a sales basis$000’s88,063 37,922 258,620 126,473 
Gold soldAu oz39,205 20,350 115,544 77,558 
Site cash costs per gold ounce sold1$/oz2,104 1,737 2,091 1,500 
Site AISC per gold ounce sold1$/oz2,246 1,863 2,238 1,631 


BOMBORÉ PRODUCTION RESULTS

Q3-2026 vs Q3-2025

Gold production increased 74% to 40,562 oz in Q3-2026 from the 23,371 oz produced in Q3-2025 as a result of a 67% increase in plant throughput as the mine benefited from the added production of the hard rock plant which was under construction in 2025.  In addition, higher plant throughput was augmented by a 4% increase in overall head grades.  The oxide plant processed 14% more tonnes in Q3-2026 as compared to Q3-2025 as mill feed consisted entirely of soft oxide ore as transition ore is now directed into the new hard rock circuit.  The higher plant throughput was offset by a decline in oxide head grades from the planned drawdown of lower-grade oxide stockpiles partially offset by higher-grade hard rock ore processed.

9M-2026 vs 9M-2025

Gold production in 9M-2026 was 116,188 oz, an increase of 46% from the 79,607 oz produced in 9M-2025.  The higher gold production is primarily attributable to a 61% increase in plant throughput partially offset by a 10% decline in head grades.  Higher plant throughput is the result of the hard rock plant start-up in December 2025 and a 13% increase in throughput of the oxide plant from the processing of softer ore.

The lower head grades in 9M-2026 as compared to 9M-2025 is due to the planned drawdown of lower-grade stockpiles for the oxide plant partially offset by higher-grade hard rock ore processed.  Oxide head grades in 9M-2025 benefitted from the sequencing of higher-grade pits in earlier periods of the mine plan and the preferential stockpiling of lower-grade ore mined. 

BOMBORÉ OPERATING COSTS

Q3-2026 vs Q3-2025

AISC per gold oz sold in Q3-2026 was $2,246, a 21% increase from $1,863 per oz sold in Q3-2025.  The increase was primarily attributable to higher government royalties driven by stronger gold prices and the revised royalty structure that took effect in April 2025.  Lower oxide head grades from the planned drawdown of stockpiles, higher strip ratio, and higher unit mining and processing costs associated wi