Highlights:
- Construction at Robex’s Kiniero Gold Project, Guinea, remains on schedule and budget - first gold pour on track for Q4 CY25.
- Project remains LTI free (lost time injury) with 3,666,920 hours worked since January 2023.
- Phase 1 grade control drilling completed at Mansounia; drilling at Sabali advancing with results pending.
- Final major concrete works completed; process plant concrete ~97% complete.
- Mill installation underway with baseplates aligned and SAG mill shell erection in progress.
- Tailings facility Phase 1A liner installation complete; mining contracts signed and equipment mobilised.
QUEBEC CITY, July 18, 2025 (GLOBE NEWSWIRE) -- West African gold producer and developer Robex Resources Inc. (“Robex” or the “Company”) (ASX: RXR | TSX-V: RBX) is pleased to provide a June 2025 project construction update for its Kiniero Gold Project in Guinea, West Africa. Robex is on track to deliver first gold at Kiniero in Q4 CY25.
- Baca Juga Robex Shareholders Approve PDI Merger
Kiniero Project Development Update – June 2025
Kiniero Construction Activities Summary
- Construction at Kiniero continues to track well against the schedule, with the majority of concrete for the process plant complete.
- Six shipments of structural steel have been received on site, with the first platework shipment expected on site within days.
- Mechanical and piping materials are arriving, which opens work fronts for the SMP contractor.
- The Power Station SMP contractor has commenced mobilisation to site, with works to commence in early August 2025.
- The Electrical and Installation team of 15 people has commenced mobilisation to site, with additional members to mobilise over the coming months as the work fronts open.
- Cable ladder installation works have commenced on the pipe racks.
Grade Control Drilling
- Phase 1 grade control drilling at Mansounia pit completed, focusing on zones identified for early-stage mining.
- Drilling at Sabali pit commenced with 16,990m drilled as at 30 June and 84,982 samples collected. Results pending.
Process Plant Construction
- Final major concrete pour completed on reclaim suspended slab. Process plant concrete is ~97% complete.
- Power station concrete progressing with 958m3 poured to date; expected completion in early August 2025.
- Field tank structures are 73% complete. Both CIL Tank Trains completed at full height; work on remaining process plant tanks commenced.
- Structural steel and platework fabrication completed, with final shipments being collected.
- SMP (Structural, Mechanical & Piping) works progressing well with 284 tonnes erected in the milling building, pipe racks, HV switch room and top of tank CIL.
Mill Installation
- Mill installation contractor has mobilised to site. Survey of both SAG and Ball mills was completed.
- Baseplates for the SAG mill trunnion bearings, pinion and drive train were installed and aligned. The erection cradle was positioned and set up for SAG mill shell erection and the bottom half of the ring gear guard installed.
- 300-tonne crane crawler assembled, with certification underway for mill component lifts.
Tailings Storage Facility
- Preparation of Phase 1A of tailings storage facility complete with 680,589m2 of liner installed.
- Construction of the main eastern embankment continues when weather permits, currently at an average level of 415m.
Mining and Infrastructure
- Mining and drill and blast contracts signed, with the first delivery of mining equipment mobilised to site.
- Geotechnical drilling for a solar farm completed; contract discussions with the provider are ongoing.
- Overland piping installation works have commenced with more than 3,500m of piping welded.
Robex’s Managing Director and Chief Executive Officer Matthew Wilcox said:
“We are now just several months away from first gold at Kiniéro in Q4, and I continue to be impressed with how the project is taking shape and the level of professionalism and safety our teams demonstrate in their work on site each day.
Many major aspects of construction are nearing completion; Phase 1 grade control drilling at Mansounia is complete and has returned high-grade gold results as reported earlier this month1, with drilling now underway at Sabali. Other components of the project, such as our tailings storage facility, are underway and progressing well.
Contractors including our mining and drill and blast teams are preparing to get to work on site, now that contracts are finalised, and their equipment is arriving on site so they can maintain our schedule for first gold.”
Next Steps
- Complete all process plant and power station concrete.
- Erection of main Mill components.
- Commence Power Station SMP works.
- Continue with erection of steelwork within the process plant.
- Continue drilling of Sabali pit.
- Award the ore haulage contract.
- Award the laboratory and power station operation and maintenance contracts.
- Complete procurement of critical, operating and maintenance spares, and reagent first fills.
Robex remains very well positioned to advance the construction of Kiniero, which remains on schedule to realise first gold production by Q4 CY25.